PWA 1996: a quick guide to its notice requirements and dispute resolution procedure

A quick guide to the Party Wall etc. Act 1996 (PWA 1996), explaining the Act's notice requirements and its section 10 dispute resolution procedure.

This is one of a series of quick guides, see Quick guides.

PLC Construction

Notice requirements under the PWA 1996

The Party Wall etc. Act 1996 (PWA 1996) provides a statutory framework (www.practicallaw.com/8-383-5739) to enable neighbours who share a boundary to carry out building works. Under the PWA 1996, a building owner (www.practicallaw.com/8-383-5739) must give notice to all adjoining owners (www.practicallaw.com/8-383-5739) of any planned works. The notice requirements (www.practicallaw.com/8-383-5739) will depend on the type of works that are to be undertaken.

Existing walls

New walls or party fence walls

Excavations

 

Adjoining owner's response to notice

How an adjoining owner may respond is determined by the type of works that are to be undertaken. The adjoining owner may:

A dispute may also arise if a building owner fails to respond to an adjoining owner's counter-notice within 14 days.

 

Section 10 dispute resolution procedure

Broadly, there are two stages to the dispute resolution procedure (www.practicallaw.com/8-383-5739) in section 10:

The parties may:

  • Agree to jointly appoint a party wall surveyor to make an award.

  • Each appoint their own party wall surveyor who will then select a third party wall surveyor. If a third party wall surveyor has been appointed, either party, or a surveyor appointed by one of the parties, may refer to that third surveyor any dispute between the building and adjoining owners.

There is no prescribed form for the award (www.practicallaw.com/7-516-5148), but it will deal with issues such as:

  • What works will be carried out.

  • When and how the works will be carried out.

  • Any additional works required by the adjoining owner.

  • A record of the condition of the adjoining owner's property before the works begin.

  • Who will pay for the costs of the award.

Over the course of a project, the surveyors may make more than one award. For example, if works cause damage to the adjoining owner's property, a further award may set out how and when it is to be repaired.

An award is final and binding on the parties and may only be overturned by an appeal to the county court. Any appeal must be made within 14 days of the award being served on the parties.

 

Key reading

Generally:

Existing walls, Standard documents:

New walls, Standard documents:

Excavations, Standard documents:


{ "siteName" : "PLC", "objType" : "PLC_Doc_C", "objID" : "1247575073402", "objName" : "PWA 1996 a quick guide to its notice requirements and dispute re", "userID" : "2", "objUrl" : "http://publicsector.practicallaw.com/cs/Satellite/4-517-0815?source=relatedcontent", "pageType" : "", "contentAccessed" : "true", "analyticsPermCookie" : "2-56125fc7:13edd21e959:-449c", "analyticsSessionCookie" : "2-56125fc7:13edd21e959:-449b", "statisticSensorPath" : "http://analytics.practicallaw.com/sensor/statistic" }